Network Refresh in Frankfurt and Dortmund: 36 Access Points in Two Days

network-refresh-cabinet-after

Network Refresh in Frankfurt and Dortmund: 36 Access Points in Two Days

In June 2025 a client asked us for a network refresh at their sites in Frankfurt and Dortmund: new Wi-Fi, a proper cable tidy, and an audit and disposal of the legacy hardware coming out. The work took two days, fitting included.

Wi-Fi survey and 36 new access points

We surveyed the floors for Wi-Fi coverage, then installed 36 new access points, testing ports as we went.

Wi-Fi coverage survey on a tablet during a network refresh
Wi-Fi coverage survey in progress

NetAlly LinkRunner AT testing a network port
Testing a port with a LinkRunner AT

192 ports re-patched

The comms cabinets needed the most work. We re-patched 192 ports from a port-by-port plan and dressed the cabling so any lead can be traced at a glance.

Comms cabinet with tangled patch leads before the network refresh
Before: the cabinet as we found it

Comms cabinet midway through re-patching
Midway through the re-patch

Engineer working from a patching plan on a laptop
Working from the port-by-port patching plan

Comms cabinet after a network refresh in Frankfurt
After: re-patched and dressed

Legacy hardware audited and cleared

Old routers, phone systems and servers were audited and removed. Most went for recycling; some RAM and disks were sold downstream once they had been processed.

Legacy routers, phone systems and servers awaiting removal
Legacy hardware audited and ready for removal

Planning a network refresh in Germany?

Read about our wireless network surveys, asset audit and valuation and work between the UK and Germany, or get in touch.