Network Refresh in Frankfurt and Dortmund: 36 Access Points in Two Days
In June 2025 a client asked us for a network refresh at their sites in Frankfurt and Dortmund: new Wi-Fi, a proper cable tidy, and an audit and disposal of the legacy hardware coming out. The work took two days, fitting included.
Wi-Fi survey and 36 new access points
We surveyed the floors for Wi-Fi coverage, then installed 36 new access points, testing ports as we went.
Wi-Fi coverage survey in progress
Testing a port with a LinkRunner AT
192 ports re-patched
The comms cabinets needed the most work. We re-patched 192 ports from a port-by-port plan and dressed the cabling so any lead can be traced at a glance.
Before: the cabinet as we found it
Midway through the re-patch
Working from the port-by-port patching plan
After: re-patched and dressed
Legacy hardware audited and cleared
Old routers, phone systems and servers were audited and removed. Most went for recycling; some RAM and disks were sold downstream once they had been processed.
The Week Europe Locked Down: A Cross-Border Data Centre Relocation
In 2020 we took on what should have been one of the more straightforward cross-border data centre relocations on our books.
A gambling operator needed around three racks of HPE equipment moved from Leeds to its sites in Gibraltar and Malta, with a backload of old hardware coming home from both for disposal. Regulated sector, fixed destinations, well-understood route. We’d done variations of it before.
Twenty-four hours after our crew crossed into Europe with the outbound load, lockdown came into force.
The job didn’t change. Everything around it did.
The equipment was the same. The destinations were the same. The client still needed it delivered.
What changed overnight was every assumption the route was built on. Which borders were open.
Which roads a commercial vehicle could use. Whether a crew could stop, where they could rest, and what quarantine rules would apply at each crossing on the way back. Rules that had been stable for years were being rewritten by the day, and sometimes by the hour, in different ways in different countries.
The plan that left Leeds was obsolete before it reached its first drop.
Hardware being dropped off in Gibraltar in March 2020
What we actually did
Nothing dramatic. We kept checking.
Before every leg, the crew and our planning desk confirmed what was legal for that specific day — not what had been true when we set off. Where a rule was unclear, we got it clarified before moving rather than assuming and finding out at a border. The deliveries went ahead, the disposal backload was collected, and the question became getting the crew home.
That meant coming back through Italy, the country hit hardest and earliest in Europe at the time. It was the leg that took the most care: confirming the vehicle could transit, what the crew could and couldn’t do on the way, and what would apply when they reached the UK.
They made it home. The equipment was delivered. The old kit came back for disposal.
What it taught us about cross-border data centre relocation
The obvious lesson is that you can’t plan for a pandemic. That’s true and not very useful.
The more useful one is that the plan is only valid on the day you check it. We’d always treated the route as something decided at the start and then executed. Since 2020 we treat it as something re-confirmed before every leg, because the conditions a move depends on — borders, access, regulations, availability — can change underneath you while the vehicle is already moving.
The second lesson is about the crew. A route that changes daily needs people on the road who can think, not just drive. The crew that went out in 2020 were making judgement calls in real time, in contact with the office, on information that was hours old. That isn’t something you can script.
Hardware being dropped off in Malta
Why it still matters
It’s tempting to file this under a once-in-a-century event. It isn’t really.
Borders and rules still change quickly, just less dramatically. Brexit rewrote the paperwork for every UK-to-Europe movement. Tariffs have moved sharply in the last year. Facility access procedures change. Carriers fail — we’ve since had an air freight provider go into administration in the middle of a job. None of it makes headlines the way 2020 did, but all of it can change what’s possible between planning a move and completing it.
The discipline is the same: confirm conditions on the day, not at the start, and put people on the road who can adapt when they change.
The question worth asking
When you’re choosing someone to move equipment across a border, the useful question isn’t whether everything will go to plan. Across enough moves, something won’t.
It’s whether they’ll know on the day, and what they’ll do about it.
DataMove vehicle filling at a completely empty fuel station en route through France
Onsite Data Erasure in France: 740 Drives and £100k Back to the Client
In 2025 a client in northern France, near Normandy, needed storage hardware retired. Half was leased and due back to the leasing company; the rest was theirs to dispose of. Every drive had to be wiped before anything left the building, so the job started with onsite data erasure.
Onsite data erasure: 740 drives
Our team erased 740 hard drives and solid-state drives on site using Blancco 5 Server, to HMG Infosec Standard 5 (Lower Standard). Drives that could not complete erasure were shredded.
Blancco 5 Server running erasure across 92 drives
Storage racks before erasure
Drive enclosures in the storage racks
Disk shelf awaiting erasure
Storage controllers and disk shelves before decommissioning
Half returned, half resold
With the data dealt with on site, the leased half went back to the leasing company clean. The rest went through targeted disposal and resale, returning over £100,000 to the client.
The trip home
With six hours to wait for the ferry from Caen, the team paid their respects at the war cemeteries and memorials that dot the Normandy coast.
Bespoke Data Engineering: Delivering 50TB of Encrypted Data on Physical Media
When a publicly listed data company needed a partner to deliver large format, heavily encrypted data sets on physical spinning disk media, they turned to DataMove.
Each project delivery so far has involved between 15TB and 50TB (terabytes!) of data, generally composed of tens of millions of heavily encrypted proprietary files. This data is housed securely in the cloud and needs a careful drawdown process, writing to physical hardware (spinning disks) and then finally delivered in person to the customer.
There were several technical constraints to overcome and find a working solution to finesse:
Rate limits on downloads from the cloud meant that traditional (naïve) transfer methods would take weeks, maybe even months — not the days that we needed to target.
Write thresholds on the destination drive hardware created bottlenecks.
The client specified a particular hardware configuration — an external device running RAID across legacy enterprise-grade spinning disks — chosen for reliability and security over raw speed.
Delivery deadlines were commercial — this was an ongoing project which needed a reliable delivery mechanism.
Our Approach
Our in-house engineers designed a bespoke solution to tackle the rate limit and throughput bottlenecks.
We developed custom Python scripts — one of which uses a partial segmentation method — to parallelise downloads in a way that both maximises sustained throughput to the spinning disks whilst respecting the source rate limits which would always be apparent in any case. This approach effectively bypasses both choke points.
We already run triple dedicated gigabit fibre pipes on lease from Openreach. This gives us essentially unlimited network capacity (with disk rates in mind) to ingest this data at scale.
The hardware build follows the client’s spec — RAID across enterprise spinning disks, specifically configured for the reliability profile the customer required. The finished projects are delivered by DataMove staff to the customer in person.
One of the RAID arrays we built for this project – this one 40TB, configured across enterprise spinning disks for reliability and secure delivery.
Why Does Any of This Matter?
It would be easy to look at this as a layman and see it as a “simple data backup”. It isn’t. This is a bespoke engineering solution with a multi-faceted custom codebase developed just for this one client and their specific data drawdown requirement. No two projects at this kind of scale could ever be the same.
The difference between taking these steps or not would ultimately be failure and an inability to deliver.
This is what “white glove service” means to us — hearing of a problem, figuring out a solution, and then actioning a deliverable time and time again.
“When we urgently needed large quantities of data transferred in ways we’d never done before, we turned to DataMove. They were able to provide a capability that was previously not possible, delivered in an extremely collaborative and timely manner.”
— Customer
The Ongoing Relationship
We have delivered multiple projects for this customer to date and the relationship continues. Every project we carry out benefits from our custom scripts and our infrastructure which is already in place.
We are continually improving this setup, which means subsequent projects run faster, with guaranteed reliability and — ultimately — predictability for the client.
If your project doesn’t fit into a standard service category — if it needs custom development, specialist hardware or a problem-solving approach — we’re happy to talk it through.
Simultaneous Server Relocations to Malta and Gibraltar for Major Gambling Operator
When a major UK-listed gambling operator needed to simultaneously relocate switch infrastructure from Northern England to Malta and server equipment from Stockholm to Gibraltar, they turned to DataMove to manage both moves end-to-end — with zero disruption to their live operations.
The Challenge
The client was consolidating infrastructure across two regulated gambling jurisdictions. The project involved two separate but simultaneous cross-border moves, each with its own customs requirements, logistics chain and installation demands:
Move 1: 14RU of Cisco switch and network infrastructure from Northern England to a data centre in Sliema, Malta — requiring full reconfiguration after reinstallation
Move 2: 20RU of server equipment from Stockholm, Sweden to a data centre in Gibraltar — requiring customs clearance at the Spanish border before entry to Gibraltar
Both moves needed to run concurrently, with equipment arriving at its destination fully operational within six days of leaving the origin site. The client wanted a completely hands-off service — one provider handling everything from deracking to customs paperwork to final verification. This was a time critical project that demanded a specialist partner.
Our Approach
DataMove managed both relocations simultaneously using our own vehicles and engineering teams. Each move followed the same structured process:
Deracking and packaging: Equipment was carefully removed from the origin racks, labelled, documented and secured in specialist flight cases for road freight
Road freight: Both shipments were transported by road in DataMove vehicles — Northern England through France, Italy and then the ferry to Malta, and Stockholm through Denmark, Germany, Belgium, Luxembourg, France, Spain and finally into Gibraltar.
Customs clearance: All export and transit documentation was prepared in advance. Malta customs was pre-booked with payments cleared before arrival, ensuring no delays at the destination. At Gibraltar, the team managed the border crossing from Spain, including a three-hour wait for paperwork to be stamped and formally exited from the EU before entry to the territory. Our forwarder partners in Gibraltar ensured all import duties were received from us and cleared before arrival.
Installation and verification: At both destinations, equipment was reracked, cabled and powered on. The Cisco switches in Malta required full reconfiguration to the client’s specifications for their new project scope. Both installations were verified via video call with the client and followed by internal checks to confirm all systems were back online
Why Downtime Wasn’t the Issue
Unlike many data centre migrations where minimising downtime is the primary concern, this project was about redeploying valuable infrastructure to new jurisdictions. The equipment being moved was staging infrastructure with redundancy already in place at third-party data centres, so live services were unaffected throughout.
The priority was retaining the value in existing hardware and reusing it at the client’s new operational bases in Malta and Gibraltar — avoiding the cost of purchasing extremely expensive new equipment while ensuring the relocated kit was fully operational on arrival.
The Outcome
Both moves were completed within six days, on schedule and without incident. The client’s infrastructure was live at both destinations, verified remotely, and the entire project was delivered with what the client described as a fully “hands-off” experience.
The project demonstrated DataMove’s ability to manage multiple simultaneous cross-border relocations across different jurisdictions — coordinating customs, logistics, engineering and client communications in parallel.
Need to Move Infrastructure Between Jurisdictions?
Whether you’re relocating servers to Gibraltar, Malta, Cyprus, Sweden or the Channel Islands, we handle the entire process — packaging, customs clearance, specialist transport and installation. One provider, one point of contact, completely hands-off.
22-Floor Cisco Network Deployment for International Law Firm
When a major international law firm with over 20 offices worldwide decided to relocate their London headquarters to a brand new skyscraper, they needed a partner who could handle the full deployment of network infrastructure across 22 floors — on time, on spec, and in a building that was still an active construction site.
The Challenge
The firm was moving from an existing London high-rise to a newly built skyscraper, occupying the top 22 floors. The project required the deployment of 20 Cisco Catalyst 9400 series Intermediate Distribution Frames (IDFs) — each one needing to be unboxed, physically installed, wired, configured, and loaded with software tailored to the client’s specific requirements.
This was not a simple equipment swap. The Catalyst 9400 series is a high-performance modular switching platform designed for enterprise-grade networks. Each unit required careful handling, precise installation, and detailed configuration work before going live. This is the kind of project that needs a specialist.
To make matters more complex, the building’s original fit-out contractor went into administration in September 2024. This caused significant delays to the overall construction programme and forced the project timeline to be restructured around the new contractor’s schedule.
DataMove Engineer Loads Cisco Config Files at Client Request
Our Approach
DataMove deployed a team of accredited engineers to work on-site across three stages of deployment over a four-week period. Given that the building was still an active construction site for much of the project, our team needed the correct PPE, site accreditations and materials to operate safely alongside other contractors.
The scope of work included:
Unboxing and physical installation of 20 Cisco Catalyst 9400 series IDFs across 22 floors
Full structured cabling and wiring to connect each IDF to the building’s network backbone
Software deployment, updates and configuration adjusted to the client’s specific network requirements
Two additional Ekahau wireless site surveys following client-requested changes to wireless access point placement
Multiple reworks to WAP positioning based on evolving client specifications as the floor layouts were finalised
Flexibility was critical throughout. The original contractor’s administration meant the project timeline shifted repeatedly, and the client made several changes to their wireless network design as the building fit-out progressed. Our team adapted to each change without compromising the overall delivery schedule.
DataMove engineer conducting Ekahau wireless site survey with London skyline view from new skyscraper office
The Outcome
Despite the disruption caused by the original contractor going into administration and multiple client-driven design changes, DataMove completed the full deployment on the adjusted schedule. All 20 IDFs were installed, configured and live across 22 floors when the firm moved into their new headquarters.
The project demonstrated DataMove’s ability to operate in challenging environments — working on an active construction site, adapting to shifting timelines, and managing scope changes — while still delivering a fully functional enterprise network infrastructure on time.
Whether you’re fitting out a new building, relocating an office, or deploying network infrastructure across multiple floors or sites, we can help. Our accredited engineers handle everything from planning through to installation, configuration and handover.
Advanced Ekahau Wireless Survey: Major Law Firm Deployment
DataMove were recently instructed to carry out comprehensive Ekahau Wireless surveys across 28 floors of a new build fit out for a major worldwide law firm, utilising the industry-leading Ekahau AI Pro solution with Sidekick 2 survey hardware.
Technical Implementation
Having already installed and configured over £6m worth of enterprise-grade Cisco connectivity infrastructure, including strategic access point deployment, our certified wireless engineers conducted the critical final verification phase. This process validated that client-specified access point locations would deliver optimal RF coverage across entire floor areas while meeting stringent security and performance requirements for the legal environment.
Trusted by 40% of Fortune 500 companies, Ekahau provided the ideal solution for this deployment. Our technical team employed active and passive survey methodologies, collecting comprehensive data on signal strength, coverage, interference patterns, and network capacity across all critical parameters.
Professional Survey Methodology
Our discreet survey teams operated with minimal disruption to ongoing activities, conducting assessments with methodical precision in the sensitive corporate environment. Using the Sidekick 2’s dual Wi-Fi radio configuration, engineers scanned comprehensively across 2.4GHz, 5GHz, and 6GHz bands with 8-hour battery life ensuring continuous operation.
The team maintained complete discretion while operating unobtrusively within the active environment, preserving sensitive client information and operational security protocols throughout the assessment process.
Survey Results and Analysis
Due to construction delays, some floors remained incomplete during initial surveys; however, comprehensive reports generated through Ekahau AI Pro’s advanced 3D capacity and coverage estimation capabilities delivered highly promising results. These analyses showcased exemplary collaboration from initial placement design through final validation surveys.
Ekahau AI Survey Pro’s map visualisation capabilities enabled detailed predictive planning off-site before on-site validation. The resulting heatmaps and reports provided actionable insights and performance guarantees for the critical wireless infrastructure investment.
Future Validation
Further targeted surveys are scheduled for two floors once construction completes, as these contain specialised heavy-duty interior installations which may impact RF propagation characteristics. Additional validation will ensure consistent coverage performance across these challenging environments.
This deployment demonstrated the exceptional capabilities of DataMove’s team combined with the Ekahau AI Pro solution, ensuring exemplary wireless connectivity across all operational sites. Our professional wireless surveys provide comprehensive facility assessment, coverage optimization, and interference analysis, delivering technical excellence for mission-critical legal operations.
For more information about our advanced wireless survey capabilities, contact DataMove today.
Project Overview: Supporting a Multinational IT Services Company
DataMove recently assisted a multinational IT services company with network refreshes and cabinet tidies/cable management on behalf of one of their clients in four European locations.
Challenges Faced: Legacy Equipment and Disorganised Infrastructure
Due to years of mixed networking strategy and staff changes, the network cabinets were in poor condition with a mish-mash of different equipment – some in use and some long since retired. The cabinets themselves were of a late 90s vintage but due to layout and sheer quantity of copper still in use these were here to stay.
Deployment Strategy: Efficient Execution Across Multiple Sites
We deployed a three man crew to Luxembourg, Frankfurt, Prague and Central London strictly out of hours and over weekend shifts to pull out 75% of the infrastructure in place and renew with Arista core and user switches as well as wireless access points followed by an Ekahau wireless survey.
Sustainable Disposal: Responsible Recycling of Outdated Equipment
Following successful completion, DataMove also organised accredited recycling services with our partners in Europe to safely dispose of the aged equipment.
Final Thoughts: Contact Us for Your Network Refresh Needs
Find some pictures of before and after below! If you need refresh/renew services, cable management and cable mapping – don’t hesitate to contact us today.
1. Gibraltar, as well as Cyprus, Malta and Sweden are popular hosting destinations for the worlds leading online gaming and sports betting companies. DataMove has worked on behalf of the biggest sports-betting companies globally in all of these locations.
2. DataMove were asked to move £250,000 worth of vital processing servers and associated equipment from two sites – Harrogate and Newport in the UK – to GibTel in Gibraltar – the British Overseas Territory.
Being high value and not to mention data sensitive equipment, the client required a dedicated van service – door to door and full rack, stack and patch both ends.
3. Project Manager Alex established a clear plan and immediately lodged an import record for the manifested goods with HM Customs Gibraltar with our preferred partner on the ground in Gib.
Prepayment of import taxes is important so as not to delay shipments into Gibraltar. Alex assigned two engineers and one of our euro spec Sprinters to carry out the work door to door in four days.
T1 documents were logged with HMRC and all paperwork’s were in place. This was a bit easier before Brexit but nonetheless standard for us now – we carry out cross border shipments weekly. Before or after Brexit, entry into Gibraltar has always been entertaining.
4. The Team carried out a full audit and port map at point of de-rack as these devices would have different elevations at the destination site. Between the two sites, there were 28 HP DL360 G10 devices and a handful of networking devices also being transported to the destination.
After a night stop at a secure compound near Folkestone, the team collected documentation near Ashford and boarded the tunnel for France. Gibraltar is a two to three day drive.
A few days later… cleared customs at La Línea de la Concepción and into Gibraltar. A relatively simple rack and stack and final ports map followed by a couple of hours remote troubleshooting to ensure our client was fully online and all devices visible.
5. Our skilled engineers ensured that this fast paced high security job was carried out in a timely and professional fashion.
Data Centres aren’t exactly glamorous but it can be nice to swing by the sunny climes of Gibraltar and Spain once in a while !
After the job was completed, this client usually has our engineers on standby for 24 hours or one full working day in case any problems arise or they require any further patching and this time it was no different.
Once this was completed, our team were back on the road and even took in a bit of sightseeing on the way back – admiring the beautiful Norman Foster creation – the Millau Bridge. What a sight to behold!
For more information about our cross border data centre relocations, contact us today!
Case Study: Crédit Agricole Bretagne Onsite Data Erasure
CLIENT OVERVIEW
Crédit Agricole “The Green Bank” is the second largest bank in France with 39 independent regional banks across France and 9,500 branches globally. The operation is a large one and naturally their data centre estate is significant.
THE CHALLENGE
DataMove were approached to help facilitate a data hall upgrade and disposal as well as secure onsite data erasure prior to activities starting. Due to staff shortages and a tight timescale with their new data hall going live, these activities needed to take place between Christmas and New Year.
DEPLOYMENT
Project Managers Andy and Tony worked together to deploy a crew, planning to travel overnight from Portsmouth to Caen on Boxing Day Evening and arriving ready to work onsite on 28th December equipped with our mobile erasure rigs, shredder (as a backup) and a fully equipped team of three engineers. The plan was to finalise erasure before returning for New Years celebrations and continuing with disposal and migration in the first week of the new year.
The six racks of Hitachi Virtual Storage Platform each containing hundreds of high capacity disks were erased using one of our three mobile Blancco rigs – designed from the ground up to be deployable within hours and able to erase hundreds of disks a day.
Being lightweight and flightcase based – we are able to express transport by Sprinter Van or even Airfreight these powerful server based rigs to our client sites globally.
With 24 hour access being issued to us by the client, our engineers were able to work in two shifts and have over 1,800 drives erased in just two days. Our rigs contain three powerful Dell servers communicating via PERC H800 cards and operating on their own temporary network, each capable of erasing hundreds of drives at a time. Any failed drives were pulled and marked and then securely erased and accounted for in our asset disposition reports. Blancco certificates are issued physically and digitally onsite.
OUTCOME
Our team were able to complete the clients data erasure requirements within the time threshold and at a tricky time of year.
The speed and accuracy of our project managers ability to fulfil the job is testament to the versatility of our engineering team and the flexibility of our modular onsite equipment that we have designed with the job – and the job only – in mind.
Our engineers even managed to stop by the Normandy beach memorial on their way back to the ferry port to pay their respects and reflect on the hardships others have suffered for our benefits.
For more information on our onsite erasure services or to get a quote, contact us today.